(Choose 1 answer)
A. Perform a root cause analysis
A development project has missed several deadlines and appears they will be missing the next one. A new project leader has been brought in. What would be the first step to get the project on track?
B. Assess individual performance by performing interviews
C. Evaluate the efficiency of the platforms being used.
D. Make a pie chart to identify a new timeline.