A development project has missed several deadlines and appears they will be missing the next one. A new project leader has been brought in. What would be the first step to get the project on track?
A. Perform a root cause analysis
B. Assess individual performance by performing interviews
C. Evaluate the efficiency of the platforms being used.
D. Make a pie chart to identify a new timeline.