(Choose 1 answer)
What is a stakeholder map used for?
A. A stakeholder map is used to keep track of the possible stakeholders a company wants to bring on to a
project in the coming year.
B. A stakeholder map is used to keep track of the interests and hobbies of the various stakeholders involved
in a project.
C. A stakeholder map is used to keep track of the influence and needs of stakeholders and the level of
communication required to work with them.
D. A stakeholder map is used to keep track of all the addresses of stakeholders involved in a project.