To develop the SIMS system, you are required to use the iterative and incremental model as project management methodology and software development model, complete for going live within 15 weeks.
Complete following 5 requests, list out your own assumptions in case you have any.
1. Request 1 (weight 20%): specify five main project stakeholders by listing out the stakeholder names and relevant detailed descriptions.
2. Request 2 (weight 20%): provide statements for five project SMART goals & give detailed explanation (about each criteria S-M-A-R-T) for each goal.
3. Request 3 (weight 20%): create the project WBS in bullet format with following 4 levels
Level 1 & 2 are the project stages/phases and their relevant iterations/sprints.
Level 3 includes the project documents (project management, engineering) and project release/deliverable names (if any) in each iteration/sprint.
Level 4 includes the work packages (screens, functions) for each release/deliverable
4. Request 4 (weight 20%): identify five project risks by listing out the risk name, description and relevant risk response plans (mitigation, contingency)
5. Request 5 (20%): you have defined and estimate project schedule with below activities
Preceding
Duration You
are requested to do the critical path analysis to Provide all the paths (from the start to the end of the project) with duration for each.
Activity
activity
in days
Start
0
Start
3
5
2
3
5
F
3
G
5
H
D, E
4
F, G
3
End
H, I
0
After 5 days, your manager/sponsor ask you to speed up so that your project would finish 3 days sooner. Please define 2 solutions with relevant explanation to achieve that (how it would help and difficulties/impacts to the project)..
Zoom FUO
120%
Time Left:116:31
Undo
Redo
Restore Screen
AutoSave every mir 1

Thông tin

Category
ECO111
Thêm bởi
Izumi2004
Ngày thêm
Lượt xem
1,664
Lượt bình luận
3
Rating
0.00 star(s) 0 đánh giá

Share this media

Back
Bên trên Bottom