(Choose 1 answer)
Report types:
Which one is the correct matching of report types and the descriptions?
(1) Status report
(2) Progress report (3) Forecasting report
Descriptions:
(a) Predicting future project progress and completion.
(b) Describing what the project team has accomplished or what is completed versus what is in progress.
(c) Describing where the project now stands.
A. (1)&(a), (2)&(b), (3)&(c)
Β. (1)&(a), (2)&(c), (3)&(b)
C. (1)&(b), (2)&(c), (3)&(a)
D. (1)&(b), (2)&(a), (3)&(c)
E. (1)&(c), (2)&(a), (3)&(b)
F. (1)&(c), (2)&(b), (3)&(a)