(Choose 1 answer)
Margo is working on a project with a tight budget and it is falling behind schedule. She wants the project to be successful, but the budget is not in her control and her company has decided to "streamline" some processes while she is still in the middle of this project. This is causing some late nights for the team.
(Choose the best answer).
A. What are some adaptive behaviors Margo could employ to keep her from getting frustrated?
B. Look for what she wants in her career and express that to her boss.
C. Avoid responsibility and blame the failure of the project on "management."
D. Take time to reflect on her life and evaluate her values.
E. Identify and focus on the positive aspects of the change, and embrace this as an opportunity to learn to
manage a challenging project.