Kizspy | Question: 36
(Choose 1 answer)
An IT system is being implemented as it has a positive NPV. However, during system development,regulations change and the project no longer has a positive NPV. The real options approach would suggest ?
A. Continue with the project, as project termination may hurt the morale of the project team
B. Terminate the project and reallocate resources to a more profitable project