3
(Choose 1 answer)
An IT system is being implemented as it has a positive NPV. However, during system development,regulations change and the project no longer has a positive NPV. The real options approach would suggest
A. Continue with the project, as project termination may hurt the morale of the project team
B. Terminate the project and reallocate resources to a more profitable project