(Choose 1 answer)
Regarding substantial performance, which of the following statements is correct?
A. If a construction contract is substantially performed, the party performing may demand the full price under the contract less the damages suffered by the other party.
B. If a contractor built a $50 million office building, none of the $50 million could be collected because of a relatively minor breach.
C. If a construction contract is substantially performed, the party performing may demand the full price under the contract plus the damages suffered by the other party.
D. If the contract price is $50 million and the damages are $5,000, the contractor will not be allowed to collect money because of the damages.
32