(Choose 1 answer)
Five batch jobs A through E, arrive at a computer center at almost the same time. They have running times of 8, 6, 2, 10, and 4 minutes. Determine the average waiting time for SJF (Shoscheduling. Ignore process switching overhead.
A. 14 minutes
B. 8 minutes
C. 6 minutes
D. 18.8 minutes
Save at server failed!. Please inform the supervisor and continue the exam.
El (24)