(Choose1 answer)
Given 14.000 USD is the most likely of the estimated cost of the activity, 8.000USD is the optimistic value and 26.000USD is the pessimistic one. By using the PERT (Program Evaluation and Review Technique) analysis to calculate the expected activity cost, which of the following is the result?
A. 16.000 USD
B. 12.000 USD
C. 15.000 USD
D. 21.000 USD
Exit 47