PMG201c_-_FA_2024_-_PE2_3165.webp
A

PMG201c_-_FA_2024_-_PE2_3165.webp

  • Media owner Alex86
  • Ngày thêm
Paper
values or you might use percentages. Derine a response for each of these risks.
Request 4 (20%): You have defined and estimate project schedule with below activities
Activity Preceding Activity Duration (weeks)
Start
0
Start
4
A, D
3
2
Start
5
4
F
2
G
C, F
6
H
5
H
9
End G, I
0
You are requested to do the critical path analysis to
Provide all the paths (from the start to the end of the project) with duration for each.Specify at least 3 solutions (with detailed explanation) to shorten this schedule 3 weeks.
Request 5 (20%): Assuming that your project was reported with the following status:
AC = $120,000;
PV = $125,000;
CV = -10,000.
Calculate and give your comments (current status, forecast and recommended adjustment) on the schedule and cost performance of the project
Zoom FUO
100%
ANSWER SHEET
SECTION 1 (Questions 1-1)
1)
Undo
Redo
Full Screen
Auto Save every minute

Thông tin

Category
PMG201c
Thêm bởi
Alex86
Ngày thêm
Lượt xem
16,081
Lượt bình luận
4
Rating
0.00 star(s) 0 đánh giá

Share this media

Back
Bên trên Bottom