All of the following are inputs to estimating activity durations except:
A. Risk Register & Scope Statement
B. Resource Calendars & Resource Breakdown Structure
C. Project Documents Updates & Requirements Specifications
D. Enterprise Environmental Factors & Organizational Process Assets