Answer (Choose 1 answer)
To calculate early start (ES) of an activity which has more than one immediate predecessors, you will
A. Take the latest late finish of its immediate predecessors.
B. Take the latest late start of its immediate predecessors.
C. Take the latest early finish of its immediate predecessors.
D. Take the latest early start of its immediate predecessors.