(Choose 1 answer)
Activity
Side 1
Side 2
Day 1
Day 2
Day 3
Day 4
Status End of Day 3
Complete, spent $1,000
You have a project to build a new fence. The fence will form a square. Each side is to take one day to build,and $1,000 has been budgeted per side. The sides are planned to be completed one after the other.
Side 3
Side 4
Complete, spent $900
50% done, spent $600
Today is the end of day 3.
Using the following project status chart to calculate
-PF 75% done, spent $600
-F
SF
-PF
PS
-PF
PS
project current CV
Key:S = Actual Start, F = Actual Finish, PS = Planned Start, and PF = Planned Finish
A. CV = $50
B. CV = $200
C. CV = $100
D. CV = $150
E. CV = $300
F. CV = $250