Answer (Choose 2 answers)
A. Direct costs: These costs are overhead items or costs incurred for the benefit of more than one project.Examples include taxes, fringe benefits, and janitorial services
B. Direct costs: These costs are directly attributable to the work on the project. Examples are team wages.team travel and recognition expenses, and costs of material used on the project.
C. Indirect costs: These costs are overhead items or costs incurred for the benefit of more than one project.Examples include taxes, fringe benefits, and janitorial services.
D. Indirect costs: These costs are directly attributable to the work on the project. Examples are team wages,team travel and recognition expenses, and costs of material used on the project.
A cost can be either direct or indirect. Which of the following statements are correct (choose 2 answers)?