ANSWER SHEET
SECTION 1 (Questions 1-1)
1) look at projec
PMG201c-Final Practice Examination #2
Look at projects that you are involved with, have been involved with OR the projects going on around you. Select one project in your studying fields at FU (i.e software project for SE), give the solutions or answers for following requests based on your understanding about the project & assumptions
Request 1: give detailed description about the project which include project title, purpose, project objectives, success criteria, start/end date, and project milestones.
Request 2: identify 3 stakeholders and decide (with relevant reasons) if they are: High power or low power; High interest or low interest; Are they unaware of the project? Are they resistant to the project?Are they neutral? Are they supportive? Are they leading?
Based on your findings, design your strategy for how you would manage these stakeholders
Request 3: Go back to the three stakeholders you identified in the request 2. Create a communication plan that includes each of these stakeholders and the communications you believe they should receive.Each communication needs to include following information: information, purpose, frequency, method or format, responsible, review by.
Request 4: Assume that you have defined and estimate project schedule with below high-level activities
Activity
Start
F
G
H
Preceding Activity
Start
A, D
Start
C, F
Duration in Months
4
3
2
5
4
2
6
5
H
Zoom
100%
I