Request 3: Go back to the three stakeholders you identified in the request 2. Create a communication plan that includes each of these stakeholders and the communications you believe they should receive.Each communication needs to include following information: information, purpose, frequency, method or format, responsible, review by.
Request 4: Assume that you have defined and estimate project schedule with below high-level activities
ANSWER SHEET
SECTION 1 (Questions 1-1)
1) look at projec
Activity
Preceding Activity
Duration in Months
Start
0
Start
4
A, D
3
2
Start
5
4
F
2
G
C, F
6
H
5
H
9
G, I End
0
a) Use the critical path analysis technique to identify the minimum duration to complete this project
b) In the 8th week, you are executing the activity D and found that you need to speed up the project schedule to recover 3-week delay. Define 2 solutions with relevant explanation and assumptions (ifneeded) to achieve that (how it would help and difficulties/impacts to the project).
Request 5: Given the following information for a one-year project after 2 months since the project start,answer the below questions: PV (Planned Value) =$22,000; EV (Earned Value) =$20,000; AC (Actual Cost)=$25,000; BAC (Budget At Completion) =$120,000
a) What are the cost and schedule performance of the project? Show your calculations.
b) How is the project doing in terms of project cost and time (schedule). Explain about those statuses c) Use the CPI to calculate the estimate the rest cost the team would need to complete the project.
d) Use the SPI to estimate how many months it will take the team to finish this project.
Zoom
100%


Q: 1

Thông tin

Category
PMG201c
Thêm bởi
Việt Hoàng1
Ngày thêm
Lượt xem
7,047
Lượt bình luận
1
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
PMG201c_-_PE2_-_SP_2024_1861.webp
File size
318.8 KB
Dimensions
1920px x 930px

Share this media

Back
Bên trên Bottom