From the schedule on request 3, after 13 weeks, your sponsor informs you that he would like to receive the product of your project earlier than your planned schedule in 5 weeks. Therefore, you must take action so that your project can finish 5 weeks sooner.
Please write down 2 solutions for this
Answer should be in this form:
Solution 1: