Request 3- Project Scheduling
Assume that you have defined and estimated project schedule with activities as below
Activity
Start
F
G
H
Preceding Activity
None
Start
Start
B, A
C, D
F, G
Duration in Weeks
0
4
3
7
8
3
3
4
7
4
0
End H, I
Draw a network diagram and identify the project duration by applying critical path analysis. Student
must determine the duration in appropriate time unit.
Notice 1: the diagram notation should be in this form.
Early Start
Duration
Early Finish
Zoom
+ 100%
Close
Activity Name
FUO
Chưa có bình luận nào.

Thông tin

Category
PMG201c
Thêm bởi
Sakura_chan
Ngày thêm
Lượt xem
2,386
Lượt bình luận
0
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
PMG201c_-_PE2_-_SU_2023_-_2_675.webp
File size
51 KB
Dimensions
1552px x 652px

Share this media

Back
Bên trên Bottom