Draw a network diagram and identify the project duration by applying critical path analysis. Student
must determine the duration in appropriate time unit.
Notice 1: the diagram notation should be in this form.
4
Early Start
Duration
Early Finish
Activity Name
Float:
Late Start
Late Finish
Notice 2: User must list out all path like below.
Path 1: Start -> A>B>... - End, duration = x weeks
Path 2: Start -> AC-...-> End, duration = y weeks
The critical path is Path x, Project duration is z weeks.
Zoom

+ 100%
Close
Chưa có bình luận nào.

Thông tin

Category
PMG201c
Thêm bởi
Sakura_chan
Ngày thêm
Lượt xem
2,417
Lượt bình luận
0
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
PMG201c_-_PE2_-_SU_2023_-_2_675.webp
File size
47 KB
Dimensions
1552px x 652px

Share this media

Back
Bên trên Bottom