Draw a network diagram and identify the project duration by applying critical path analysis. Student
must determine the duration in appropriate time unit.
Notice 1: the diagram notation should be in this form.
4
Early Start
Duration
Early Finish
Activity Name
Float:
Late Start
Late Finish
Notice 2: User must list out all path like below.
Path 1: Start -> A>B>... - End, duration = x weeks
Path 2: Start -> AC-...-> End, duration = y weeks
The critical path is Path x, Project duration is z weeks.