Notice 2: User must list out all path like below.
Path 1: Start -> A>B>... End, duration = x weeks
Path 2: Start -> AC-...-> End, duration = y weeks
The critical path is Path x, Project duration is z weeks.
Request 4-Schedule Updating & Tracking
From the schedule on request 3, after 10 weeks, your sponsor informs you that he would like to receive the product of your project earlier than your planned schedule in 5 weeks. Therefore, you must take action so that your project can finish 5 weeks sooner.
Please write down 2 solutions for this request.
Answer should be in this form:
Colution 1.