Request 4 (weight 35%)
Assume that you have defined and estimate schedule for one of main project deliverables
with below high-level activities as following:
Preceding Activity
Activity
Start
Start
A, D
Start
F
G
C, F
H
1
End
H
G, I
Duration in Weeks
0
4
3
2
5
4
2
6
5
a. What are paths in the network diagram for the deliverable?
b. Identify the minimum duration to complete that deliverable?
9
0
c. What are activities which have the most flexibity (in term of time)?
d. In the 8th week, you are executing the activity D and found that you need to speed up the
project schedule to recover 3-week delay. Define at least four solutions with relevant
explanation and assumptions (if needed) to achieve that.
Zoom FUO
100%
ANSWER SHEET
SECTION 1 (Questions 1-1)
1)
Undo
Redo
Full Screen
Auto Save every minute

Thông tin

Category
PMG201c
Thêm bởi
pink_happiness1
Ngày thêm
Lượt xem
17,292
Lượt bình luận
8
Rating
0.00 star(s) 0 đánh giá

Share this media

Back
Bên trên Bottom