Ex: Path 1: Start -> A > B > C... -> End
Path 2: Start -> ABC-> End
Path n: Start -> ABC..-> End
Request 4-Schedule Updating & Tracking
From the schedule on request 3, after 3 weeks, your sponsor inform you that he would like to receive the product of your project earlier than your planned schedule in 5 weeks. Therefore, you have to find the solutions so that your project could finish 5 weeks sooner.
Define at least 4 solutions and set the priority order for them, and include relevant explanation how it will help your project to be developed faster to accomplish on time.
Request 5-Cost Evaluation
There is a senior project manager who asked you to give him your estimation about the status of a project while training you as a junior project manager. The manager gives you the basic information of the project that is:
1. The cost of project was estimated at ten thousand USD ($10,000)
2. He planned that a team can complete the project in 30 days.
3. After 6 days, he got a report that 25% of the project jobs completed.
4. The total spend for the project at that time was two thousand USD ($2,000).
5. He said that he planned the completion work load and amount of spend equally for everyday from the beginning to the end of the project.