Request 2-milestone & deliverable
Based on your WBS, you are requested to identify at least 5 milestone for the project. For each milestone, write a short description, list out at least 2 deliverables corresponding with milestone and propose your estimated duration
Sample:
Milestone
Description
Initiation
Plannning Execution 1
Release verion 1.0 with 2 features
Init project
Deliverables
Project charter
Assumption log
Estimated Duration
1 week
Do project planning
Request 3-Project scheduling
Activity
Preceding Activity
Duration in Weeks
Start
0
Start
10
1
5
7
C, D
6
F
5
G
1
H
G, F
10
G
2
End
H, I
0
Assume that you have defined and estimate project activities with above high level activities
Please make an critical path analysis report which:
Providing all the paths (from start to end of the project) with duration for each path.
Determine critical path and project duration
List out Early Start, Early Finish, Late Start, Late Finish, Float of each activity of the project (thefirst activity has an early start of 1)
Chưa có bình luận nào.

Thông tin

Category
PMG201c
Thêm bởi
dungroi
Ngày thêm
Lượt xem
2,556
Lượt bình luận
0
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
PMG201c_-_SU2023_-_PE_-_FUDA_684.webp
File size
70 KB
Dimensions
945px x 1943px

Share this media

Back
Bên trên Bottom