Assume that you have defined and estimate project activities with above high level activities
Please make an critical path analysis report which:
Providing all the paths (from start to end of the project) with duration for each path.
Determine critical path and project duration
List out Early Start, Early Finish, Late Start, Late Finish, Float of each activity of the project (thefirst activity has an early start of 1)
Request 4-Schedule Adjusting
After 15 weeks, your sponsor ask you to speed up and finish the project 5 weeks sooner. Please define 2 solutions with relevant explanation to achive that (how it would help and difficulties, impacts to the project). You can provide your assumption for your explanation if needed
Request 5-performance analysis
You are PM of a project with 100M VND budget and 12 weeks duration.
After 4 weeks, you check the records and find out that you have spent 40M VND with 40% work completed.
Please do an Earn Value Analysis and give your comments:
Current status (above/behind schedule? Under/over budget?)forecast
recommend adjustments

Thông tin

Category
PMG201c
Thêm bởi
dungroi
Ngày thêm
Lượt xem
2,113
Lượt bình luận
1
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
PMG201c_-_SU2023_-_PE_-_FUDA_684.webp
File size
22.2 KB
Dimensions
453px x 545px

Share this media

Back
Bên trên Bottom