Answer (Choose 1 answer)
As a project manager, you're prioritizing stakeholders with a power grid. One stakeholder has low power and high interest. What level of engagement should the team have with the stakeholder?
A. Monitor
B. Meet their needs
C. Show consideration
D. Manage closely