Answer (Choose 1 answer)
Which of the following scenarios best represents a project that is going out-of-scope?
A. The deliverable to present your project's pre-launch event at a three-day, in-person conference is now an online conference.The switch reduces the costs associated with event space, travel, and people resource tim.
B. During the project weekly meeting, the project sponsor adds a new deliverable requirement that costs $10,000 USD. This addition surpasses the budget by $5,000USD.
C. During the project weekly meeting, the project manager learns the main vendor will increase the cost of raw materials by 20%due to an international shortage
D. The manufacturer of one of the project deliverables just lost power after a large storm. They don't expect to be in production for one week, delaying the project timeline.
E50