Kizspy | Question: 28 (Choose 1 answer)
Which scenario is an example of planned cost versus actual cost?
A. When planning your project budget, you notice that you need to advertise several job positions. The cost to post the job descriptions to several online job boards is $300.
B. When planning your project budget, you document the planned cost of labor. To do this, you use the estimated number of hours your team needs to complete the project. As your project progresses, you document the total hours your team works to determine the total cost of labor for your project. This number may be different from your original cost of labor.
C. When planning your project budget, you gather historical data on costs of materials, resources, and labor to determine how much each will cost. Once you begin procuring these items, you don't update the actual cost.
D. When planning your project budget, you need to factor in unexpected costs that may occur. You decide to
reserve 5% of your overall budget as a buffer.
  • Like
Reactions: linhmy

Thông tin

Category
PMG202c
Thêm bởi
Todoroki_87
Ngày thêm
Lượt xem
679
Lượt bình luận
1
Rating
0.00 star(s) 0 đánh giá

Share this media

Back
Bên trên Bottom