Kizspy | Question: 30
(Choose 1 answer)
As a project manager, you're identifying task dependencies. Task B cannot finish until Task A is complete-the tasks operate at the same time. Which type of dependency does this situation represent?
A. Finish to Finish (FF)
B. Start to Finish (SF)
C. Finish to Start (FS)
D. Start to Start (SS)