Complete following 4 requests, list out your own assumptions in case you have any.
1. Request 1 (weight 20%): specify five main roles in your project teams by listing out the role names and relevant detailed descriptions.
2. Request 2 (weight 20%): identify five project risks by listing out the risk name/description and relevant risk response plans (mitigation, contingency)
3. Request 3 (20%): you have defined and estimate project schedule with below activities
Preceding Activity
Duration (weeks)
You are requested to do the critical path analysis to
Activity
• Provide all the paths (from the start to the end of the project) with duration for each.
Start
0
Start
3
• Specify at least 3 solutions (with detailed explanation) to shorten this schedule 3 weeks.
5
2
3
5
F
3
G
5
H
D, E
4
F, G
3
End
H, I
0
4. Request 4 (weight 40%): list out five user stories (1-2 user stories for a role) for the project. The description for each user story needs to include: User Story Title, User Story Details (in the form of "As a... I need/want to... so that..."), and Acceptance Criteria (list out at least two criteria for each user story)