PMG202c_-_PE1_-_SP_2024_1805.webp
Obanai891

PMG202c_-_PE1_-_SP_2024_1805.webp

PMG202c - Practical Exam 1 (Spring 2024)
The ABC company is a growing organization that specializes in the development of software solutions for various clients. The company has experienced significant growth over the past few years, and with the increase in business comes the need for a better way to manage projects. Currently, they rely on spreadsheets and other manual methods to manage projects, which can be time-consuming and error-prone. In order to streamline project management, the ABC company has decided to invest in a new Project Management System (aka PMS, support the project managers, team members and other project stakeholders on following management area: scope/requirement, schedule/time,cost/budget, quality, issue, and communication) and they have hired your team to design and develop this system with the target to complete for going live (system operation) officially after 7 months. The PMS should be scalable to handle increasing numbers of projects and stakeholders.
To develop the PMS system, you (the project manager) and your team decide to use Agile/Scrum as project management methodology and software development model, planned to have 4 main releases which respectively provide the system functionalities for 4 project roles: system admin,project manager, team member, and customer.
Given the system accesses (use cases) to the Team Member actor are as listed below
View tasks assigned to them, track time, and update progress.
View and update project scope, project requirements Report expenses and view project budget and financial reports
Contribute to project quality, including testing and reporting issues.
Complete following 5 requests, list out your own assumptions in case you have any.
1. Request 1 (weight 20%): specify five main roles in your project teams by listing out the role names and relevant detailed descriptions.
2. Request 2 (weight 20%): list out all the user stories for the Team Member actor in the form of "Asa... I want to... So That..."
3.Request 3 (weight 20%): create the project WBS in bullet format with following 4 levels
Level 1 & 2 are the project stages/phases and their relevant iterations/sprints.
Level 3 includes the project documents (project management, engineering) and project release/deliverable names (if any) in each iteration/sprint.
Level 4 includes the work packages (screens, functions) for the release/deliverable of Team Member actor-related use cases.
4. Request 4 (20%): Identify five project risks by listing out the risk name, description and relevant risk
response plans (mitigation, contingency)
100%
ANSWER SHEET
SECTION 1 (Questions 1-1)
1)
Zoom


I want to nisin the exam.

Q: 1
Chưa có bình luận nào.

Thông tin

Category
PMG202c
Thêm bởi
Obanai891
Ngày thêm
Lượt xem
643
Lượt bình luận
0
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
PMG202c_-_PE1_-_SP_2024_1805.webp
File size
422.4 KB
Dimensions
1920px x 930px

Share this media

Back
Bên trên Bottom