PMG202c- Practical Exam 4 (Fall 2023)
You are working on a project to develop an online Sales and Inventory Management System (SIMS) for a departmental store. There are registered people in the system and each of them may have some exclusive
privileges on the system functionalities as below
The Sales people: see the status of the inventory, enter the items purchased by a customer and produce a bill for the same, cancel the produced bill
The inventory manager: check the status and validate the inventory, generate reports
The sales manager: check the bills, transferred money, returning items and the reports
The administrator: add new items/categories to the inventory, change the price of an item
develop the SIMS system, you are required to use the iterative and incremental model as project
To management methodology and software development model, complete for going live within 15 weeks.
Complete following 5 requests, list out your own assumptions in case you have any.
1. Request 1 (weight 20%): specify five main project stakeholders by listing out the stakeholder names and relevant detailed descriptions.
2. Request 2 (weight 20%): provide statements for five project SMART goals & give detailed explanation (about each criteria S-M-A-R-T) for each goal.
3 . Request 3 (weight 20%): create the project WBS in bullet format with following 4 levels
Level 1 & 2 are the project stages/phases and their relevant iterations/sprints.
Level 3 includes the project documents (project management, engineering) and project release/deliverable names (if any) in each iteration/sprint.
Level 4 includes the work packages (screens, functions) for each release/deliverable
4. Request 4 (weight 20%): identify five project risks by listing out the risk name, description and relevant risk response plans (mitigation, contingency)
5. Request 5 (20%): you have defined and estimate project schedule with below activities
Activity
Start
activity
Start
120%
Duration You are requested to do the critical path analysis to in days
0
3
5
Provide all the paths (from the start to the end of the project) with duration for each.
After 5 days, your manager/sponsor ask you to speed up so that your project would finish 3 days
Zoom FUO
Preceding
Time Left:116:25
Undo
Redo
Restore Screen
AutoSave every mir 1
Chưa có bình luận nào.

Thông tin

Category
PMG202c
Thêm bởi
Thúy Hằng
Ngày thêm
Lượt xem
502
Lượt bình luận
0
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
PMG202c_-_PE22_-_FA_2023_1229.webp
File size
141 KB
Dimensions
1926px x 906px

Share this media

Back
Bên trên Bottom