2. Request 2 (weight 20%): identify five project risks by listing out the risk name/description and relevant risk response plans (mitigation, contingency)
3. Request 3 (20%): you have defined and estimate project schedule with below activities
Activity
Start
F
G
H
End
Preceding Duration
You are requested to do the critical path analysis to Provide all the paths (from the start to the end of the project) with duration for each.
activity in days
Start
A, D
Start
C, F
H
G.I
4
3
2
5
4
2
6
After 5 days, your manager/sponsor ask you to speed up so that your project would finish 3 days sooner. Please define 2 solutions with relevant
explanation to achieve that (how it would help and difficulties/impacts to the project).
1) Request 1
Scrum master: they are responsible for coaching team members to use agile and scrum practices, facilitating scrum events such as sprint retrospective
9
0
4. Request 4 (weight 40%): list out five user stories for the project (1-2 user stories for a role). The description for each user story needs to include: User Story Title, User Story Details (in the form of "As a... I need/want to... so that..."), and Acceptance Criteria (list out at least two criteria for each user story)
81%
vt fini

Zoom

Chưa có bình luận nào.

Thông tin

Category
PMG202c
Thêm bởi
Khánh Duy1
Ngày thêm
Lượt xem
628
Lượt bình luận
0
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
PMG202c_-_PE2_-_FA_2023_1230.webp
File size
60.2 KB
Dimensions
1372px x 594px

Share this media

Back
Bên trên Bottom