You are requested to do the critical path analysis to
Provide all the paths (from the start to the end of the project) with duration for each.
Specify at least 3 solutions (with detailed explanation) to shorten this schedule 3 weeks.
5. Request 5 (20%): your project team have completed a workload equivalent to $3,000 and has spent $4,000 to date. Assume you were budgeted $5,000 for the work scheduled. Calculate and give your comments (current status, forecast and recommended adjustment) on the schedule and cost of the project