A project manager forgets to assess how national holidays and team member vacations will affect the project's completion date. Now, because of team member time off, the project delivery will be two weeks late.What flexible planning strategy could the project manager have used to avoid the delay?
A. Enable decision-making
B. Escalate to stakeholders
C. Assessing external constraints
D. Use collaboration tools