Suppose as a project manager you're receiving requests from stakeholders to add new features to the product you're developing. How would you deal with this external scope creep?
A. Implement the initial stakeholders requests and then ban all future requests.
B. Agree on who can make formal requests and how your team will evaluate and act on those requests.
C. Ignore the requests because the project is already underway.
D. Take a team vote to decide if the team should add the new feature to the product.