Imagine you are a project manager creating release plans for a new cloud storage service. Your team is performing well, so you decide to push up the estimated release date. Which specific factors do you take into account to make your decision?
A. The team's willingness and work ethic
B. The team's experience and the customer's timeline
C. The team's capacity and velocity
D. The team's size and the customer's budget