Choose the best definition for inherent risk as it relates to project management.
A. The measure of a risk, calculated by its difficulty and frequency
B. The measure of a risk, calculated by its timing and dependencies
C. The measure of a risk, calculated by its probability and impact
D. The measure of a risk, calculated by its causes and circumstances