Given the system accesses (use cases) to the Team Member actor are as listed below
View tasks assigned to them, track time, and update progress.
View and update project scope, project requirements
Report expenses and view project budget and financial reports
Contribute to project quality, including testing and reporting issues.
Complete following 5 requests, list out your own assumptions in case you have any.
1. Request 1 (weight 20%): specify five main roles in your project teams by listing out the role names and relevant detailed descriptions.
2. Request 2 (weight 20%): list out all the user stories for the Team Member actor in the form of "Asa... I want to... So That..."
3. Request 3 (weight 20%): create the project WBS in bullet format with following 4 levels
Level 1 & 2 are the project stages/phases and their relevant iterations/sprints.
Level 3 includes the project documents (project management, engineering) and project release/deliverable names (if any) in each iteration/sprint.
Level 4 includes the work packages (screens, functions) for the release/deliverable of Team Member actor-related use cases.
4. Request 4 (20%): you have defined and estimate project schedule with below activities
Activity
Start
F
G
H
Preceding Activity
Start
A, D
Start
C, F
Duration (weeks)
0
4
3
2
5
4
2
6
5