Level 1 & 2 are the project stages/phases and their relevant iterations/sprints.
Level 3 includes the project documents (project management, engineering) and project release/deliverable names (if any) in each iteration/sprint.
Level 4 includes the work packages (screens, functions) for the release/deliverable of Team Member actor-related use cases.
4. Request 4 (20%): you have defined and estimate project schedule with below activities
Activity
Start
F
G
H
End
Duration (weeks)
0
4
3
2
5
4
2
6
5
9
0
Preceding Activity
Start
A, D
Start
C. F
H
G, I
You are requested to do the critical path analysis to
Provide all the paths (from the start to the end of the project) with duration for each.Specify at least 3 solutions (with detailed explanation) to shorten this schedule 3 weeks.
5. Request 5 (20%): The planned value (PV) for your project is $5000. After five months, you do a performance measurement analysis and finding that the actual cost for the project is $6500 while only 80% of the project scope is complete. Calculate and give your comments (current status, forecast and recommended adjustment) on the schedule and cost performance of the project