Paper
FU (via the Software Tools Department) has hired your team to build this system with the target to complete to be ready for going live (used officially) after 15 weeks. The FOL system should be scalable to handle increasing numbers of students, courses or course contents, and the learning transactions.
To develop the FOL system, you (the project manager) and your team decide to use iterative and incremental as project management methodology and software development model.
Complete following 5 requests, list out your own assumptions in case you have any.
1. Request 1 (weight 20%): specify five main project stakeholders by listing out the stakeholder names and relevant detailed descriptions.
2. Request 2 (20%): define the RACI chart where you list out five tasks or deliverables; For each task/deliverable, list out the responsibilities of the project stakeholders.
3. Request 3 (weight 20%): provide statements for five project SMART goals & give detailed explanation (about each criteria S-M-A-R-T) for each goal.
4. Request 4 (weight 20%): identify five project risks by listing out the risk name, description and relevant risk response plans (mitigation, contingency)
5. Request 5 (weight 20%): create the project WBS in bullet & in/outdent format with below 4-5 levels
Level 1 is the project itself;
Level 2-3 are project stages/phases and relevant iterations;
Level 4 includes project management tasks and project deliverables;
Level 5 includes the work packages (screens, functions) of the relevant deliverable.
100%
ANSWER SHEET
SECTION 1 (Questions 1-1)
1)
Full Screen
Auto Save every minute
Undo
Redo
Chưa có bình luận nào.

Thông tin

Category
PMG202c
Thêm bởi
Vanessa_88
Ngày thêm
Lượt xem
619
Lượt bình luận
0
Rating
0.00 star(s) 0 đánh giá

Share this media

Back
Bên trên Bottom