Kizspy | Question: 28
(Choose 1 answer)
A video analytics organization has been acquired by a leading media company. The analytics organization has 10 independent applications with an on-premises data footprint of about 70TB for each application. The CTO of the media company has set a timeline of two weeks to carry out the data migration from on-premises data center to AWS Cloud and establish connectivity.
Which of the following are the MOST cost-effective options for completing the data transfer and establishing connectivity? (Select two)
A. Order 1 Snowmobile to complete the one-time data transfer
B. Order 10 Snowball Edge Storage Optimized devices to complete the one-time data transfer
C. Setup Site-to-Site VPN to establish on-going connectivity between the on-premises data center and AWS Cloud
D. Order 70 Snowball Edge Storage Optimized devices to complete the one-time data transfer
E. Setup AWS direct connect to establish connectivity between the on-premises data center and AWS Cloud