Kizspy | Question: 12
(Choose 1 answer)
When computing the NPV of a capital budgeting project, one should NOT:
A. estimate the cost of the project.
B. discount the future cash flows over the project's expected life.
C. ignore the salvage value.
D. make a decision based on the project's NPV.