Question: 6
(Choose 1 answer)
What should be done if new costs are identified after the initial risk mitigation plan has been created?
A. Ignore the new costs
B. Recalculate the cost-benefit analysis
C. Immediately implement the countermeasures
D. Cancel the risk mitigation plan