Kizspy | Question: 31
(Choose 1 answer)
Which of the following is not an example of a question that should be asked when evaluating a supplier's
production scheduling and control systems?
A. Does the supplier use a requirements planning system as part of an ERP system to ensure the availability
of required components or meet service requests on a timely basis?
B. What lead time does the supplier's production scheduling and control system require?
C. What is the supplier's on-time delivery performance history?
D. Does the supplier's scheduling system support a purchaser's delivery requirements?
E. What safeguards are in place to protect the confidentiality of electronic transfers?