Kizspy | Question: 46
(Choose 1 answer)
(9910)In value stream mapping, the flow diagram that depicts the process and shows the times and resources used at each step and the time delay between each step is called a/an
A. anticipated state map
B. future state map
C. ideal state map
D. current state map
E. None of the above.