(Choose 1 answer)
A. projectitis
A(n)is a specific point in the project plan when a task and its action steps are complete and have a noticeable impact on the progress of the project plan as a whole.
B. milestone
C. RFP (Request For Proposal)
D. WBS (Work Breakdown Structure)
E. None of the mentioned