The FU-NextExam is a new development system, so there may be many changes during the development process. With the experienced resources of the FU's IT department, the FU's leaders intend that the project will be undertaken by the IT department and the development team participating in the project will include 4-5 extensive experience and skills developers. Managers of other departments commit to sending employees to join the project team to support project completion with high quality.
FU leadership expects the first version of the system to be put into use within 3 months and the project needs to be completely completed within 8 months.
Assume you are assigned to implement this project, you should read carefully the above description of the project then answer these questions:
1. What software development methodology would you suggest for this situation and
why?
(2 points)
Identify the project characteristics (user, customer, team, requirements characteristics, time constraints and managers' expectation)
Select a development model that best fits the factors you identified above.
2. What type and level/stage of testing would you suggest the team to do? Who will do test in each test level/stage? (1 point)
3.List four functional requirements and two non-functional requirements that have been

+ 100%
Zoom
Close
Chưa có bình luận nào.

Thông tin

Category
SWE201c
Thêm bởi
Olivier2005
Ngày thêm
Lượt xem
3,341
Lượt bình luận
0
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
SWE201c_-_PE1_-_SP_2024_-_s_-_1_1820.webp
File size
317.8 KB
Dimensions
1920px x 820px

Share this media

Back
Bên trên Bottom