Kizspy | Question: 32
(Choose 1 answer)
In your current project, you have access to some intern development resources, which are not currently
operating at full capacity. You also know that the testing timeline will be truncated, due to delays in critical-path
module development. Which strategy should you employ?
A. Allow the testing team to work without (or with quick-to-develop) drivers and stubs, and utilize the intern
resources to aid testing once all critical-path development is complete
B. Utilize the intern resources to design and develop drivers and stubs, while work continues on critical-path
module development
C. Allow the testing team to work without (or with quick-to-develop) drivers and stubs, while using intern
resources to aid critical-path development
D. Make no changes to the current project testing or development allocations, utilizing intern resources to
create documentation.